Howard Creek Bridge Replacement:
- Location: Near the fire station on Highway 50
- Duration: Through October
- Details: 24/7 one lane closure controlled by temporary traffic signals
- Expected Delays: 15-minute hold times
Ongoing Resurfacing:
- Location: Highway 50 from Salida to Howard
- Details: Combined with the Howard Creek Bridge work, expect 30 to 45 minutes of extra travel time
Weather-Related Issues:
- Area: Canyon between Texas Creek and Canon City
- Details: Heavy rain has caused flooding and rock slides—exercise caution
Additional Construction Delays:
- Highway 50/285 Intersection in Poncha Springs: Expect considerable delays due to construction
- Oak Street in Salida: Full closure continues due to ongoing construction